|
Granduc - The Tunnel
Phase
1
In September, 1964, tunnel driving began. The tunnel,
through which ore travels from the mine at Leduc to the mill at Tide
Lake, passed under three glaciers and three mountain ranges up to 7,000
feet high. Because this tunnel would be the life line of Granduc, it had
to be designed for fast, large-scale, safe transportation of people, ore
and supplies. Fifteen feet in diameter and carrying a high-speed
railroad system, the tunnel was to be driven by two crews working from
each end, planning to meet at the midpoint.
And so
they would have, had not Nature stepped in. The Tide Lake heading at the
planned site of the concentrator was no great problem insofar as
supplying men and materials was concerned. However, at the mine end, at
the Leduc Glacier, the tunnel crews faced real hardships. To reach the
Leduc camp where the crews lived that first winter, one drove nine miles
from Stewart to Cantu at the foot of the Salmon Glacier, then boarded
tractor-drawn sled trains for a 22-mile run up the glacier and over a
5,500-foot ice-filled pass to Leduc.
By February, 1965, the men
at Leduc had driven just 28 feet of tunnel. That month, an avalanche
roared down on Leduc, killing 26 crew members and wrecking much of the
camp at the tunnel portal. Although a thorough Government investigation
cleared Granduc Mines of any negligence or safety violation, the company
halted work at Leduc, and brought in a renowned avalanche expert to
advise the company on measures to avoid future avalanche damage. His
recommendations were scrupulously followed.
At about
the same time as the avalanche, detailed engineering work had begun to
indicate that the Granduc project would be considerably more expensive
than originally estimated. Furthermore, driving the tunnel from one end,
which now seemed necessary, greatly increased the expense, as did the
avalanche control measures instituted. In short, Granduc, in 1965, faced
severe financial, as well as technical, problems.

|